Skim coat removed from the kitchen and dining room walls before new drywall
Example project
- Home
- 1950s house in Lynwood with plaster walls in the kitchen and the dining room
- Original request
- Strip both rooms back and hang new drywall
- Testing
- A Cal/OSHA-certified asbestos consultant samples the skim coat, the base plaster and the compound at the window trim
- Found
- Asbestos in the skim coat on both rooms’ walls
- Clear
- The base plaster and the trim compound
- Area
- About 400 sq ft of wall
- Timeline
- Notice no later than 10 working days ahead, then three working days
- Cost
- $4,800
Scope of work
Samples of each layer, the district notice, both rooms sealed with air filters running, the skim coat removed wet, bagging and the haul. The clearance air test, the new drywall and the paint are separate.
Project overview
In this example, the owners of a 1950s house in Lynwood are opening up the kitchen and dining room walls for new drywall and wiring. The plaster has a thin skim coat that was added over the years.
The skim coat tests positive and the base plaster is clear. The abatement crew takes the skim coat off both rooms, and the drywall crew starts after the air results.
The goal
The goal is bare plaster in both rooms, so the new drywall goes up with the old skim coat gone.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples the walls in both rooms.
- Before work The abatement contractor files the district notice online and the owners empty both rooms.
- Days one to three The rooms are sealed and the skim coat is removed from the walls wet.
- Last An independent consultant tests the air, then the drywall crew starts.
Planning right
- Empty the cabinets and take down the window coverings.
- Plan to cook elsewhere for the three work days.
- Hold the drywall delivery until the air results.
- Keep the lab report with the permit papers.